Kerajang-Angul doubling track to be commissioned in January

Kerajang-Angul doubling track to be commissioned in January

Bhubaneswar: The doubling of 13.5 km track between Kerajang and Angul, a part of the doubling of Sambalpur-Talcher link, is likely to be commissioned in the first week of January.
The doubling between Kerajang and Angul is on the verge of completion and the inspection by Commissioner of Railway Safety is to be conducted by the end of this month, East Coast Railway (ECoR) sources said. In view of loading, this line is very important as it will have a surge from 3 MT to 6 MT from Jindal Steel Plant Limited (JSPL) siding.
This doubling is a part of 85.3 km Rairakhol to Angul doubling work of Sambalpur-Talcher Road railway line. With this, almost 51 per cent of Sambalpur-Talcher Road doubling will be completed.